FEES FOR THE GRANT OF A LICENCE FOR A FACTORY FOR ONE YEAR
Horse Power Installed | Maximum number of workers to be employed any day during the year | |||||||
---|---|---|---|---|---|---|---|---|
Up to 20 | 21 to 50 | 51 to 100 | 101 to 250 | 251 to 500 | 501 to 750 | 751 to 1000 | Above 1000 | |
Rs. | Rs. | Rs. | Rs. | Rs. | Rs. | Rs. | Rs. | |
Nil | 100 | 200 | 400 | 1000 | 1600 | 3000 | 4000 | 5000 |
Up to 10 | 200 | 400 | 480 | 1200 | 2400 | 3600 | 4800 | 6000 |
Above 10 and Up to 50 | 400 | 600 | 800 | 2000 | 4000 | 6000 | 8000 | 10000 |
Above 50 and Up to 100 | 800 | 1000 | 1200 | 3000 | 6000 | 9000 | 12000 | 15000 |
Above 100 | 1200 | 1600 | 2000 | 4000 | 8000 | 12000 | 16000 | 20000 |
Note: The above fee schedule was substituted and notified vide Notification dated 03.04.2001 and comes into force w.e. f. 1st January, 2001 in respect of grant and renewal of licence.